Connect with us

News

Completion date for repairs to £32m King’s Dyke bridge pushed back

Avatar photo

Published

on

More work than was first thought necessary means contractors will not finish remedial work on the £32m King’s Dyke bridge, Whittlesey, until July.

Cambridgeshire County Council made the announcement of being contacted by CambsNews after we published photographs of the work in progress.

“The remedial work to the verge at the top of the embankment has been progressing well, although it has been necessary for the contractor to remove and replace material at a lower level than initially anticipated,” said a council spokesperson.

“The work has also been restricted by the availability of road space due to other works needing to take place in the area.

“We’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned.”

In April the council announced remedial work would begin on the bridge – known as Ralph Butcher Causeway – starting on 19 April for nine weeks “although we hope to finish sooner if possible”.

Advertisements
canopyuk.com in-article

However, with the extra work now needed, the council has explained that the mid-June deadline has been extended to July.

“Following our post in April, we explained we were carrying out remedial work and at the end of any major scheme there is a period where final checks are completed,” said the spokesperson.

The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris


Cambridgeshire County Council says of King’s Dyke ‘we’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned’ PHOTO: Terry Harris

“Last year, there was a focus on Star Pit and a piled wall was installed below ground level.

“That work allowed the road’s embankment to be built on top.

“As part of that final check, Cambridgeshire County Council and Jones Bros agreed further work was required at the top of the embankment.”

The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris


Cambridgeshire County Council says of King’s Dyke ‘we’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned’ PHOTO: Terry Harris

The spokesperson explained that the remedial work involves:

  • Removing the safety barrier and fence between the rail bridge and the underpass structures
  • Replacing the top 1.2m of verge
  • The installation of drainage
  • Reinstalling the safety barrier

“We’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned,” said the spokesperson.

Council dismisses visual ‘assessment’

The council has also dismissed a visual ‘assessment’ of the bridge made by an engineer who contacted CambsNews after seeing our recent photographs.

The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris


Cambridgeshire County Council says of King’s Dyke ‘we’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned’ PHOTO: Terry Harris

The engineer wrote: “From looking at the photos my guess is that once again the clever consultants have ignored the difficulties of building anything in Fenland with its very high-water table and poor ground stability.

“They get this wrong every time despite the examples of the concrete guided busway at Impington, Fen Drayton and the piling needed to support the embankment on the Ely Southern Bypass.

The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris

The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris

“The views in the article quite clearly indicate that the work in hand is to stabilise the road embankment which appears to be visibly subsiding at one point. In other words, the underlying fen ground conditions will not support the weight of the concrete road structure and safety barrier.

“The whole lot appears to by migrating towards the excavated water filled pit at the right-hand side of the picture. You will note that where the road crosses the railway the Bridge abutments are deep piled to take the weight of the concrete span.

“The circular piles are clearly visible in the construction sequence still photos.

“One shudders to contemplate yet another legal action against the design and build contractors as the final product is clearly defective and unfit for purpose.”

 But his observations have been dismissed by the county council.

“As for the engineer comments – ‘the whole lot appears to be migrating’ this is not correct,” said the council spokesperson.

“Our monitoring records collected in the months before the remedial work started indicated that the carriageway was not affected.

The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris


Cambridgeshire County Council says of King’s Dyke ‘we’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned’ PHOTO: Terry Harris

“Hence why the material at the top of the verge is being replaced.

“The problem is believed to have occurred because the fill material originally used is not draining as expected.

“A different class of material is being used and a land drainage feature has also been included in replacement.”

The spokesperson also took issue with the observation that “the final product is clearly defective and unfit for purpose”.

The spokesperson said: “This is also not correct. We’re not sure what photos the engineer is commenting on, but the matter has been picked up as per our contract, it’s been investigated, further design work has been carried out and remedial work is being done to address it.

The £32m King’s Dyke crossing at Whittlesey opened in July of last year – six months ahead of schedule. The project team announced on April 12 that they were to begin a nine-week programme of “remedial work”. PHOTO: Terry Harris


Cambridgeshire County Council says of King’s Dyke ‘we’re aiming to finish all the work in July, although the remedial work to the embankment should be completed in June as planned’ PHOTO: Terry Harris

“The road won’t be fully completed until the contractor has completed all work, including remedial work, on site.

“The county council will be keeping the situation under review and if there are any further signs of movement following the reconstruction these will be followed up with the contractor in the normal way as per the contract.”

The spokesperson added: “We are carrying out the work as quickly as possible, and we thank everyone for their patience.”

 

 

Can you help us?

While you’re here, we are asking, for the first time, for readers to support us financially by taking out a modest subscription.

£2, or £3 or even £5 will help us achieve our goals. It will mean the second year of CambsNews will be livelier, healthier, and much better placed to cover the important issues affecting our everyday lives.

Your subscription simply means we can provide and expand our news FREE to all readers (Read More)

Will you help us? Simply click the link below to make a donation.

Facebook

Read More

Firefighters stage protest in Huntingdon over reduction in reduction to fire crews PHOTO: Mark Thomas Firefighters stage protest in Huntingdon over reduction in reduction to fire crews PHOTO: Mark Thomas
News12 hours ago

HRH The Princess Royal finds one’s way interpreted by protesting firefighters

Cambridgeshire firefighters stage protest in Huntingdon

Iliran Sinani with the car he was driving and the drugs found in a laundry basket Iliran Sinani with the car he was driving and the drugs found in a laundry basket
Crime14 hours ago

WATCH: Drug dealer caught with £45k worth of cannabis in Ford Transit

Nine bags containing cannabis worth up to £45,000 was discovered in the car

At a ceremony held at Troxy in London, the judges gave Stagecoach East the Gold Award in the Bus and Community category for its work on Behind the Buses. At a ceremony held at Troxy in London, the judges gave Stagecoach East the Gold Award in the Bus and Community category for its work on Behind the Buses.
News15 hours ago

Stagecoach East wins ‘gold’ award for numbers attracted to visit its bus depots

Stagecoach East earlier won the trophy for Excellence in Road Safety, Traffic Management and Enforcement

A strategy to improve buses so that the number of passenger journeys doubles by 2030. This includes a range of improvements, from more electric buses to significant change to how services operate from the current deregulated system. A strategy to improve buses so that the number of passenger journeys doubles by 2030. This includes a range of improvements, from more electric buses to significant change to how services operate from the current deregulated system.
News15 hours ago

Wayne’s exit allows for approval of vital new transport strategy for Cambridgeshire and Peterborough

One aim of the LTCP is to set out future transport options where there is support and a good case...

Cllr Anna Bailey points an angry finger at Mayor Dr Nik Johnson. “He should resign,” she says. Cllr Anna Bailey points an angry finger at Mayor Dr Nik Johnson. “He should resign,” she says.
News17 hours ago

Mayor Nik Johnson threatens ‘formal action’ against Tory council leader for ‘impropriety’ claims

'In your public comments you have cast aspersions against me as a practising doctor' Mayor tells Cllr Bailey.

Bake Off photo: Channel 4 / Mark Bourdillon / Love Productions Bake Off photo: Channel 4 / Mark Bourdillon / Love Productions
News1 day ago

Peterborough teacher is 2023 Great British Bake Off winner

Channel 4 described Matty as the type of baker “who swats up on online patisserie videos before bed

Residents in Terrington St Clement say health and safety has “gone mad” after their local council placed yellow warning tags on gravestones. PHOTO: Terry Harris Residents in Terrington St Clement say health and safety has “gone mad” after their local council placed yellow warning tags on gravestones. PHOTO: Terry Harris
News2 days ago

37 gravestones in Fens village – some brand new – ‘unsafe’ as residents claim health and safety ‘gone mad’

'Who seriously sat down with the H&S team stifling a laugh when they said ‘these leaning stones are a risk''?

King’s College, Cambridge, has started placing solar panels on its iconic 15th century Chapel – despite opposition from local residents and organisations, including Historic England. PHOTO: BavMedia King’s College, Cambridge, has started placing solar panels on its iconic 15th century Chapel – despite opposition from local residents and organisations, including Historic England. PHOTO: BavMedia
News2 days ago

Residents ‘devastated’ as King’s College, Cambridge, puts 492 solar panels on its roof

King’s College, Cambridge, has begun placing solar panels on its iconic 15th century chapel – despite opposition from residents and...

UNISON Eastern regional secretary Tim Roberts said: “The care system would implode without migrant care staff. Demonising these workers will do nothing to solve the social care crisis. UNISON Eastern regional secretary Tim Roberts said: “The care system would implode without migrant care staff. Demonising these workers will do nothing to solve the social care crisis.
News2 days ago

Union demands Government averts adult social care disaster after collapse of Cambridgeshire care home

A visa extension would allow overseas care workers more time to find new employment, says UNISON

Sample of the plans for conversion of Nags Head, Eastrea, into a village shop. Highways official say they not acceptable Sample of the plans for conversion of Nags Head, Eastrea, into a village shop. Highways official say they not acceptable
News2 days ago

Cambridgeshire village shop plans ‘lack clarity’ ‘illegible’ and create ‘confusion’

Whittlesey town council is recommending refusal